"This is great work. My company spends a handful of time trying to get lead time data from manufacturers. This is a one stop shop to get live lead time for major power equipment."
A quarterly intelligence product for utility project controls engineers and procurement managers. Cite the matrix in your schedule basis — not a vendor email.
| SUB-CLASS | WKS | QoQ | YoY | CONF |
|---|---|---|---|---|
| GSU 500 kV | 142 | ▲ 4 | ▲ 28 | A |
| GSU 230 kV | 118 | ▲ 2 | ▲ 22 | A |
| Power TX 138 kV | 96 | ▼ 2 | ▲ 14 | B |
| SF6 Breaker 230 kV | 78 | ▲ 1 | ▲ 9 | A |
| MV Switchgear 15 kV | 54 | ▼ 3 | ▲ 4 | A |
| Pad-mount TX 25 kV | 46 | ▼ 0 | ▼ 2 | B |
Current-quarter lead times across all tracked equipment classes, with QoQ / YoY deltas, 12-month forecast, supplier concentration, and confidence grade per row.
Overlay up to six equipment classes. Historical curves, forecast cones, and recession-style shading. Built to be screenshotted into a board deck.
Enter required in-service dates. Get the latest order-by date per equipment class, with quantity, review time, and shipping factored in. Export to CSV.
"This is great work. My company spends a handful of time trying to get lead time data from manufacturers. This is a one stop shop to get live lead time for major power equipment."
"Finally a defensible reference for transformer lead times. I cite the matrix directly in schedule basis memos instead of guessing from vendor emails."
"The QoQ and YoY deltas on GSU classes match what we are seeing in the field. The confidence grades keep me honest about where the data is thin."
"Schedule impact calculator is exactly the artifact we needed for capital project reviews. Would love driver attribution at the sub-class level next."
Built for project controls engineers and procurement managers at US electric utilities. The Q2 2026 release is available to beta testers now.